MIA-03 - Service migration
Scheduled on 2018-11-17 08:00:00 Status Completed MaintenanceFollowing previous incident:
- https://clients.gestiondbi.com/index.php?/status/18//
- https://clients.gestiondbi.com/index.php?/status/19//
We will proceed with the migration of all customers VPS to a new datacenter in the same region. Take note, there is no IP change associated with this migration.
For any questions, please contact our team at http://gdbi.pw/contact
Related servers / services
MIA-03
Date | Action |
---|---|
2018-11-16 18:35:00 | Our Systems Administrators are currently tuning the latest details on the server preparation. |
2018-11-16 20:02:00 | New server is ready to received the customers. |
2018-11-16 20:16:00 | Migration will take place tomorrow, November 17, 2018 at 8h00 GMT-5 |
2018-11-17 07:56:00 | We start the maintenance by turning off all VPS prior the migration. |
2018-11-17 08:27:00 | All VPS are turned off. We start migrating |
2018-11-17 09:19:00 | Migration is going well. BGP switch is scheduled for 10h00 GMT-5 |
2018-11-17 09:58:00 | BGP Session will be switch in a few minutes... |
2018-11-17 10:09:00 | BGP session are swapped. Already migrated VPS will start to recover slowly. |
2018-11-17 12:30:00 | Almost half of the VPS has been migrated and are online |
2018-11-17 12:30:00 | IPv4 BGP session is up and running |
2018-11-17 12:30:00 | IPv6 BGP session is still under propagation |
2018-11-17 13:05:00 | More than 70% of the VPS has been migrated |
2018-11-17 13:54:00 | More than 90% of VPS are migrated |
2018-11-17 14:05:00 | All VPS are now active on the new server. IPv4 network is fully operationnal. We are awaiting for the IPv6 to kick in completely. |
2018-11-18 12:36:00 | Everything is back to normal. In case of issue, please contact our support team. |